Modern Mining Plans 40,000-Ounce E-Waste Recovery Plant in North Carolina


Modern Mining Plans 40,000-Ounce E-Waste Recovery Plant in North Carolina

 

Modern Mining Plans 40,000-Ounce E-Waste Recovery Plant in North Carolina

MONTREAL (RecyclingMonster): Modern Mining Technology Corp. (NYSE American: MDRN) has announced an 18-month development program for its first commercial-scale electronic waste metals recovery operation in North Carolina, targeting annual design capacity of approximately 40,000 gold-equivalent ounces.

The project follows the company's approximately US$40 million initial public offering, completed on November 12, 2026. Modern Mining plans to use its proprietary aqueous-based processing technology to recover gold, silver, copper and other valuable metals from discarded electronics.

Key Points

  • US$40 million IPO: Modern Mining completed its offering on November 12, 2026, to support commercial expansion.
  • 40,000 gold-equivalent ounces: The proposed facility targets this annual production capacity, subject to successful construction and ramp-up.
  • One tonne per hour: The planned pre-concentration unit is designed to process waste printed circuit boards at this rate.
  • 41 product lots: The Greenville demonstration facility settled 41 recovered-metal concentrate lots between December 2023 and June 2026.
  • 18-month plan: Development includes construction, commissioning, commercial production growth, supply agreements and pursuit of R2 certification.

US$40 Million IPO Supports Commercial E-Waste Expansion

Modern Mining closed its initial public offering on November 12, raising approximately US$40 million to support expansion of its electronic waste recovery operations.

The proposed commercial facility builds on the company's research and demonstration activities in Greenville, North Carolina, where it has recovered and sold metal concentrates from electronic waste since November 2023.

Between December 2023 and June 2026, the Greenville operation settled 41 product lots containing recovered metal concentrates.

These results provide experience in material processing and concentrate sales, although the company's proposed commercial production capacity remains a development target rather than an achieved operating result.

North Carolina Plant Targets One Tonne of Circuit Boards Per Hour

Modern Mining plans to construct a pre-concentration plant and an aqueous purification facility in North Carolina during the first six to nine months of its development program.

The pre-concentration plant is being designed to process up to one tonne of waste printed circuit boards per hour.

According to the company's development schedule, commissioning and capacity ramp-up are targeted during months nine to twelve, followed by expansion of commercial production and revenue during months twelve to eighteen.

The proposed facility will recover precious and commodity metals using the company's aqueous-based processing technology.

Modern Mining also plans a centralized purification system capable of accepting recovered-metal concentrates from as many as five regional pre-concentration plants. The company believes this approach could reduce transportation and operating costs as additional processing locations are developed.

Feedstock Partnerships and R2 Certification Remain Priorities

Securing reliable electronic waste supplies will be important to the proposed plant's commercial operations.

Modern Mining plans to establish binding procurement agreements with recyclers, e-waste aggregators, manufacturers, original equipment manufacturers and IT asset disposition providers.

The company also intends to pursue R2 Responsible Recycling certification during the development period.

R2 certification addresses responsible electronics recycling practices, including environmental management, worker protection, data security and downstream handling of materials.

The certification has not yet been confirmed as obtained. Modern Mining expects its Greenville demonstration facility to continue supporting process development and operator training during the commercial build-out.

Commercial-Scale E-Waste Processing Faces Execution Challenges

Modern Mining's proposed expansion reflects growing interest in recovering gold, silver, copper and other valuable metals from end-of-life electronics and printed circuit boards.

However, expanding from a demonstration operation to commercial-scale production requires sustained material throughput, reliable feedstock procurement, consistent metal recoveries and commercially viable operating costs.

Key milestones will include completing construction, establishing supply agreements, commissioning processing equipment and demonstrating production at the targeted design capacity.

The company's announced 18-month timetable remains subject to construction, permitting, technology performance, financing and market conditions.

 

 

 

 

 