Waga Energy Plans 120 GWh Landfill RNG Facility in Indiana
MONTREAL (RecyclingMonster): Waga Energy has signed a long-term agreement with Randolph Farms Landfill and Best Way Disposal, both part of The Balkema Companies, to develop a renewable natural gas (RNG) production facility in Modoc, Indiana.
The project will use Waga Energy's WAGABOX technology to process up to 3,200 cubic meters of landfill gas per hour and produce as much as 120 GWh of renewable natural gas annually. Commissioning is targeted for early 2028.
Key Points
- 20-year agreement: Waga Energy will finance, construct, own and operate the Randolph Farms RNG facility for at least 20 years.
- 120 GWh annually: The planned WAGABOX unit will process up to 3,200 cubic meters of raw biogas per hour at full capacity.
- Early 2028: Commissioning is scheduled for the beginning of 2028, with RNG intended for interstate pipeline distribution.
- 31,700 tons CO2e: Waga Energy estimates the project could avoid approximately this amount of greenhouse gas emissions annually.
- Second Indiana partnership: The project follows Waga Energy's Decatur Hills RNG facility in Greensburg.
Waga Energy Signs 20-Year Randolph Farms RNG Agreement
Under the agreement, Waga Energy will finance, build, own and operate the landfill gas upgrading facility for a minimum of 20 years.
Randolph Farms Landfill will manage landfill gas collection and support civil construction. The partners will share revenue generated from renewable natural gas sales.
The Randolph Farms Landfill has operated under The Balkema Companies since 1986, providing waste disposal services to communities in eastern Indiana and neighboring areas of Ohio.
The agreement marks the second renewable natural gas collaboration between Waga Energy and The Balkema Companies, following their Decatur Hills project in Greensburg, Indiana.
WAGABOX Facility to Produce Up to 120 GWh of RNG Annually
The planned installation will use Waga Energy's patented WAGABOX technology, which combines membrane separation and cryogenic distillation to convert landfill gas into pipeline-quality renewable natural gas.
At full operating capacity, the unit is designed to process approximately 2,000 standard cubic feet per minute, equivalent to 3,200 cubic meters per hour, of raw landfill gas.
Annual renewable natural gas production could reach approximately 407,000 MMBtu (120 GWh).
The new system will replace the existing gas upgrading installation at Randolph Farms. The landfill currently produces RNG for Best Way Disposal's onsite vehicle fueling operations.
Under the new project, the upgraded gas will be directed to a nearby interstate pipeline for distribution into natural gas markets, including transportation fueling.
Waga Energy expects the facility to begin commissioning in early 2028.
Project Targets 31,700 Tons of Avoided Emissions Annually
According to Waga Energy, the Randolph Farms installation is expected to avoid approximately 31,700 tons of carbon dioxide-equivalent emissions annually through the production and use of renewable natural gas.
The estimate represents the company's projected environmental benefit. Actual emissions performance will depend on operating conditions, methane recovery, gas production and end-market use.
Decatur Hills RNG Facility Establishes Indiana Operations
Waga Energy's first partnership with The Balkema Companies resulted in the Decatur Hills RNG facility in Greensburg, Indiana.
The facility began operating in July 2026 and was officially inaugurated during a ribbon-cutting ceremony on October 21, 2026.
Developed with Decatur Hills Landfill and Best Way Disposal, the plant uses WAGABOX technology to upgrade methane-rich landfill gas previously directed to flaring.
The facility can process up to 1,000 standard cubic feet per minute of landfill gas and is designed to produce approximately 203,000 MMBtu of RNG annually at full capacity.
The recovered gas is injected into CenterPoint's local natural gas distribution network through a dedicated pipeline connection and marketed by U.S. Energy.
Waga Energy estimates that the Decatur Hills project can avoid more than 15,800 metric tons of CO2-equivalent emissions annually.
The facility was financed and constructed by Waga Energy, which will own and operate it for at least 20 years.
With the Randolph Farms agreement, Waga Energy is extending its Indiana operations through a second long-term landfill gas recovery project.