Lake County Approves Meadowview Waste Transfer Facility to Replace Grayslake Landfill


Lake County Approves Siting for Meadowview Material Transfer Facility

MONTREAL (RecyclingMonster):

A proposed waste transfer facility in Lake County, Illinois, has obtained a key local regulatory approval, subject to a total of 13 conditions. The facility could replace the Countryside landfill in Grayslake when the site closes in 2028. Waste Management submitted a 1,959-page application earlier this year.

The Lake County Board approved Waste Management of Illinois Inc.'s local siting application for the proposed Meadowview Material Transfer Facility. The company can now move forward to the Illinois Environmental Protection Agency (IEPA) for a permit for the project. Readers can track ongoing developments in the sector on the RecyclingMonster homepage, which covers waste and recycling industry news nationwide.

Facility Size and Waste Capacity

The proposed facility would occupy 11 acres east of Route 83, directly south of the existing landfill. It will have capacity to handle up to 1,000 tons of nonhazardous municipal waste per day.

The facility houses a 31,540-square-foot enclosed building, where waste will be stored before being transferred. The project also includes a recycling center, which is intended to replace Grayslake's existing drop-off site for electronics, clothing, textiles and food scraps on Berry Avenue.

Permitting Timeline and Construction Outlook

According to officials, the construction phase of the facility is expected to be approximately 18 months, upon receipt of necessary permits. Waste Management expects to obtain required state and county permits by early 2027, with construction targeted for spring 2027.

What This Approval Means for Grayslake Residents

The siting approval marks a significant step for a facility designed to serve Grayslake and the surrounding area after the Countryside landfill closes in 2028. With the local siting application now approved subject to 13 conditions, the project's path forward depends on Illinois EPA permitting and the timelines Waste Management has outlined for construction. For readers tracking regional scrap and recycling market activity, RecyclingMonster's U.S. scrap metal prices page offers current pricing data from yards across the country, while those looking to responsibly dispose of an old vehicle can review options through RecyclingMonster's cash-for-junk-cars service.

Frequently Asked Questions
What is the Meadowview Material Transfer Facility?

It is a proposed 11-acre waste transfer facility in Grayslake, Illinois, designed to handle up to 1,000 tons of nonhazardous municipal waste per day and potentially replace the Countryside landfill when it closes in 2028.

Who submitted the siting application?

Waste Management of Illinois Inc. submitted a 1,959-page siting application, which the Lake County Board approved subject to 13 conditions.

What is the next regulatory step for the project?

Waste Management must now obtain a permit from the Illinois Environmental Protection Agency (IEPA) before the project can proceed further.

Will the facility include a recycling center?

Yes. The project includes a recycling center intended to replace Grayslake's existing Berry Avenue drop-off site for electronics, clothing, textiles and food scraps.

When could construction begin and how long will it take?

Waste Management expects to receive state and county permits by early 2027, with construction targeted to start in spring 2027 and take about 18 months to complete.