Greenwood County, Redtail Renewables Advance Landfill RNG Project


Greenwood County, Redtail Renewables Advance Landfill RNG Project

The planned South Carolina facility is designed to process approximately 1,250 standard cubic feet of landfill gas per minute and produce about 300,000 MMBtu of renewable natural gas annually once fully developed.

Published September 16, 2026

Key Points

  • Greenwood County and Redtail Renewables are advancing a renewable natural gas project at the Greenwood County Landfill.
  • Redtail acquired VRNG Greenwood LLC, the project's previous developer, in a transaction completed in late July.
  • The planned facility is designed to process approximately 1,250 standard cubic feet of landfill gas per minute.
  • Annual RNG production is expected to reach approximately 300,000 MMBtu once the facility is fully developed.
  • The amended county agreement calls for construction to begin by the end of 2027 and be completed by the end of 2028.

MONTREAL (RecyclingMonster): Greenwood County, South Carolina, and Redtail Renewables are moving ahead with plans to develop a renewable natural gas (RNG) project at the Greenwood County Landfill.

The partnership follows Redtail Renewables' acquisition of VRNG Greenwood LLC, the company previously developing the facility. The transaction closed in late July, with Redtail assuming responsibility for investment in and operation of the landfill's gas collection system under long-term agreements with the county.

Landfill Gas to Be Upgraded Into Pipeline-Quality RNG

The project will capture landfill gas generated by decomposing waste and process it into pipeline-quality renewable natural gas.

Greenwood County and Redtail said the resulting RNG is intended for use as a lower-carbon transportation fuel.

Facility Designed for 300,000 MMBtu of Annual RNG Production

Once fully developed, the facility is designed to process approximately 1,250 standard cubic feet of landfill gas per minute and produce about 300,000 MMBtu of RNG per year.

According to the project announcement, the anticipated emissions impact is comparable to removing the carbon dioxide emissions associated with nearly 2,000 passenger vehicles from the road each year.

County Agreement Sets 2028 Project Completion Deadline

Greenwood County's amended landfill-gas agreements provide for a project determination phase through March 2027.

Under the amended timeline, project construction is required to begin by the end of 2027 and be completed by the end of 2028.

 

People Also Ask

What is Greenwood County's landfill RNG project?

Greenwood County and Redtail Renewables plan to capture landfill gas and upgrade it into pipeline-quality renewable natural gas.

How much RNG could the Greenwood County facility produce?

The planned facility is designed to produce approximately 300,000 MMBtu of renewable natural gas per year once fully developed.

How much landfill gas will the facility process?

The project is designed to process approximately 1,250 standard cubic feet of landfill gas per minute.

Who is developing the Greenwood County RNG project?

Redtail Renewables is developing the project after acquiring VRNG Greenwood LLC in late July 2026.

When is the Greenwood County RNG project expected to be completed?

The amended county agreement calls for construction to be completed by the end of 2028.